Planning a garage pad or detached garage in Parkland County? This free guide explains the permit order, required drawings, the 592 sq ft engineering rule, lot grading requirements, and approach permit standards.

Planning a garage pad or detached garage in Parkland County? This free guide explains the permit order, required drawings, the 592 sq ft engineering rule, lot grading requirements, and approach permit standards.

What’s Inside the Parkland County Garage Permit Guide

What’s Inside the Parkland County Garage Permit Guide

• Development Permit vs Building Permit order
• The 12-month rule after Development Permit approval
• When engineering is required for a slab-on-grade
• Required drawings for a detached garage
• Lot grading requirements in Parkland County
• Residential driveway approach width standards

• Development Permit vs Building Permit order
• The 12-month rule after Development Permit approval
• When engineering is required for a slab-on-grade
• Required drawings for a detached garage
• Lot grading requirements in Parkland County
• Residential driveway approach width standards

Why Most Garage Projects Get Delayed

Why Most Garage Projects Get Delayed

Most delays happen because something small was missed early.


Incomplete site plans.
Slab size triggering engineering.
Drainage requirements discovered after concrete is poured.
Starting work before permits are issued.


Understanding the Parkland County development permit process and the Parkland County building permit for a detached garage before you start can save weeks of frustration.

Most delays happen because something small was missed early.


Incomplete site plans.
Slab size triggering engineering.
Drainage requirements discovered after concrete is poured.
Starting work before permits are issued.


Understanding the Parkland County development permit process and the Parkland County building permit for a detached garage before you start can save weeks of frustration.

Garage Pad and Detached Garage Permits in Parkland County

Garage Pad and Detached Garage Permits in Parkland County

If you are building a garage pad in Parkland County, most projects require a Parkland County development permit followed by a Parkland County building permit for a detached garage.


All applications are submitted through PLANit Parkland.

After your Development Permit is approved, you have 12 months to apply for your Safety Codes permits. If you wait longer, your Development Permit can become invalid.

Depending on your property and scope of work, lot grading in Parkland County may also apply.

If you are building or modifying your driveway access, an approach permit must be approved before construction, and residential approach widths typically range from 6.0 meters minimum to 8.0 meters maximum.

If you are building a garage pad in Parkland County, most projects require a Parkland County development permit followed by a Parkland County building permit for a detached garage.


All applications are submitted through PLANit Parkland.

After your Development Permit is approved, you have 12 months to apply for your Safety Codes permits. If you wait longer, your Development Permit can become invalid.

Depending on your property and scope of work, lot grading in Parkland County may also apply.

If you are building or modifying your driveway access, an approach permit must be approved before construction, and residential approach widths typically range from 6.0 meters minimum to 8.0 meters maximum.

Need Help Planning Your Garage Properly?

Need Help Planning Your Garage Properly?

Prairie Acre Developments offers free on-site consultations for acreage owners.


We help you:

• Confirm setbacks and layout
• Plan drainage correctly
• Lay out garages to scale
• Prepare permit-ready drawings
• Identify when engineering may be required


If you want your garage project to move smoothly through approval and construction, book a free on-site consultation.

Prairie Acre Developments offers free on-site consultations for acreage owners.


We help you:

• Confirm setbacks and layout
• Plan drainage correctly
• Lay out garages to scale
• Prepare permit-ready drawings
• Identify when engineering may be required


If you want your garage project to move smoothly through approval and construction, book a free on-site consultation.

Planning Guide Below

Planning Guide Below

Parkland County Garage Permit Guide

Garage Pad + Detached Garage | Acreage Quick Reference


Permit Order

• Development Permit (Planning)

• Building Permit (Safety Codes)

• Apply through PLANit Parkland.

• 12 months after Development Permit approval to apply for Safety Codes permits.

• Starting work without required permits may result in doubled fees.


May Also Be Required

• Lot Grading – If grades or drainage are affected.

• Approach Permit – Required before modifying driveway access.

• Residential approach standard: 6.0m minimum, 8.0m maximum.


Development Permit Package

• Recent Land Title

• Site Plan (property lines, setbacks, buildings)

• Floor Plan (dimensions + door/window openings)

• Elevations (all sides, height, roof slope)

• Accessory building totals (existing + proposed)


Building Permit Package

• Structural details (foundation, framing, roof)

• Slab specifications

• Engineering required if slab ³ 592 sq ft (55 sq m)


Common Reasons for Delays

• Incomplete drawings or missing documents

• Inconsistent measurements between plans

• Engineering not provided when required

• Drainage or lot grading discovered late

• Approach permit overlooked


Need Help?

• Prairie Acre Developments offers free on-site consultations.

• We assist with site layout, drainage planning, and permit-ready drawings.

Parkland County Garage Permit Guide

Garage Pad + Detached Garage | Acreage Quick Reference


Permit Order

• Development Permit (Planning)

• Building Permit (Safety Codes)

• Apply through PLANit Parkland.

• 12 months after Development Permit approval to apply for Safety Codes permits.

• Starting work without required permits may result in doubled fees.


May Also Be Required

• Lot Grading – If grades or drainage are affected.

• Approach Permit – Required before modifying driveway access.

• Residential approach standard: 6.0m minimum, 8.0m maximum.


Development Permit Package

• Recent Land Title

• Site Plan (property lines, setbacks, buildings)

• Floor Plan (dimensions + door/window openings)

• Elevations (all sides, height, roof slope)

• Accessory building totals (existing + proposed)


Building Permit Package

• Structural details (foundation, framing, roof)

• Slab specifications

• Engineering required if slab ³ 592 sq ft (55 sq m)


Common Reasons for Delays

• Incomplete drawings or missing documents

• Inconsistent measurements between plans

• Engineering not provided when required

• Drainage or lot grading discovered late

• Approach permit overlooked


Need Help?

• Prairie Acre Developments offers free on-site consultations.

• We assist with site layout, drainage planning, and permit-ready drawings.